Nuclear-for-AI datacenter deal book

Every publicly announced deal where a hyperscaler or datacenter operator secures nuclear power — restarts, PPAs, behind-the-meter and SMR orders — translated from megawatts into modeled annual pounds of U₃O₈. The AI-era demand story, quantified for uranium investors. Every deal is source-linked. Related: the SMR pipeline → and the policy & waiver ledger →

Capacity announced

33.3 GW

8.8 GW firm (signed / operating)

Incremental U₃O₈

Modeled

12.4 Mlb/yr

14.7 Mlb/yr gross deal-associated · 1.6 Mlb/yr firm incremental

Deals tracked

20

14 hyperscaler buyers

Ramp

12.0 Mlb

modeled by 2039

Announced ≠ contracted ≠ new demand. The two largest entries — Switch–Oklo (12 GW) and Amazon–X-energy (5 GW) — are multi-year option frameworks running to 2039–2044, not firm baseload. The firm figures count only binding contracts, restarts under construction, and operating-plant PPAs. And a PPA with an already-operating plant (Susquehanna, the Vistra fleet, Clinton) changes who buys the power, not how much uranium the reactor consumes — those deals contribute only their documented uprate megawatts to the incremental figures, and deals sharing the same physical reactors (a master agreement and its first tranche) count once. Each row's event type, status and note say which is which.
BuyerPower sourceTypeCapacityU₃O₈ / yr (modeled)CODStatusSource
SwitchOkloAurora powerhouse fleetppanew build12,000 MW5.30 Mlb2029announcedSwitch press release
Amazon (AWS)X-energyXe-100 (national fleet)investmentnew build5,000 MW2.21 Mlb2039signedX-energy press release
MetaTerraPowerNatrium (up to 8 units)investmentnew build2,800 MW1.24 Mlb2032signedPOWER Magazine
MetaVistraPerry, Davis-Besse, Beaver Valleyppaexisting plant2,609 MW1.15 Mlb0.19 Mlb incremental2026signedPOWER Magazine
Endeavour (Edged data centers)Deep FissionDeep Fission borehole PWRmounew build2,000 MW0.88 Mlb2029announcedWorld Nuclear News
Amazon (AWS)Talen EnergySusquehanna Steam Electric Stationppaexisting plant1,920 MW0.85 Mlb0.00 Mlb incremental2026signedsource
Standard PowerNuScale Power / ENTRA1 EnergyNuScale VOYGR (Ohio & Pennsylvania)mounew build1,848 MW0.82 Mlb2029announcedsource
MetaOkloAurora campus, Pike County, Ohioppanew build1,200 MW0.53 Mlb2030signedPOWER Magazine
MetaConstellation EnergyClinton Clean Energy Centerppaexisting plant1,121 MW0.50 Mlb0.01 Mlb incremental2027signedsource
MicrosoftConstellation EnergyCrane Clean Energy Center (ex-TMI Unit 1)restartrestart835 MW0.37 Mlb2028under-constructionUtility Dive
GoogleNextEra EnergyDuane Arnold Energy Centerrestartrestart615 MW0.27 Mlb2029under-constructionsource
GoogleKairos PowerKP-FHR fleet (Master Plant Development Agreement)ppanew build500 MW0.22 Mlb2030signedsource
EquinixOkloAurora powerhouseppanew build500 MW0.22 Mlb—announcedsource
Amazon (AWS)Energy NorthwestCascade Advanced Energy Facility (Xe-100, Richland WA)smr-ordernew build320 MW0.14 Mlb—announcedsource
Amazon (AWS)Dominion EnergySMR near North Anna Power Stationmounew build300 MW0.13 Mlb—announcedsource
GoogleTennessee Valley Authority / Kairos PowerHermes 2 (Oak Ridge, TN)ppanew build50 MW0.02 Mlb2030under-constructionsource
NvidiaValar AtomicsWard 250 (30 MW waterless AI factory)mounew build30 MW0.01 Mlb—announcedDeseret News
EquinixRadiant NuclearKaleidos microreactorsmr-ordernew build———announcedEquinix newsroom
Fermi AmericaWestinghouse (AP1000)Project Matador / HyperGrid, Amarillo TXbehind-the-meternew build———announcedData Center Dynamics
OracleUndisclosed vendorThree SMRs for a 1+ GW AI data centerbehind-the-meternew build———announcedCNBC

Methodology

Modeled

Annual uranium demand per deal is MODELED from disclosed nuclear capacity: MW (nameplate) / 1000 = GWe; multiplied by 170 tU/GWe/yr (industry standard, ~85% capacity factor, per the site demand model) and by 0.0026 Mlb U3O8/tU (model v2). Gross deal-associated fuel (all disclosed MW, overlap-deduped) is reported separately from INCREMENTAL fuel vs the operating-fleet baseline: eventType classifies each deal (existing-ppa / restart / uprate / new-build / life-extension), existing-plant PPAs contribute only their uprate share (incrementalMw), and deals sharing physical capacity carry an overlapGroup so a master agreement and its first tranche never double count. bindingStatus separates binding PPAs from frameworks/MOUs; only binding deals with firm status enter firm totals. Cancelled deals and deals with undisclosed capacity are excluded from the demand rollup. Capacities and dates are the operators' own disclosed figures where available.

Deal capacities and dates are the operators' own disclosed figures where available; every deal links to its primary source. Deals without a verifiable source do not ship, and those with undisclosed capacity are listed but excluded from the demand rollup — we do not guess. The uranium translation is modeled, not a quote. To convert megawatts into uranium demand yourself, the reactor-fuel guide walks the math end to end. See full methodology.

The gigasite, in uranium pounds

Reactor-fleet visions, translated into the only unit that matters here: pounds of U₃O₈ a year. Pick a scenario or set your own fleet.

Modeled

Illustrative take on the thousands-of-reactors gigasite vision, at the announced AI-factory unit size.

Fleet capacity

30.0 GW

U₃O₈ demand (modeled)

13.3 Mlb/yr

5,100 tU/yr

Of world mine supply

8.5%

of 2024 production (157 Mlb)

Vs the AI deal book

0.90×

the announced total above

Modeled, not a forecast: nameplate MWe × 170 tU per GWe-year (~85% capacity factor, LWR fuel cycle) × 0.0026 Mlb U₃O₈ per tU — the same constants as the deal book and the site demand model. Advanced designs' real fuel cycles (HALEU enrichment levels, burnup, load factors) will differ; treat results as order-of-magnitude context, not procurement math.

Free report: The AI-Nuclear Uranium Demand Report

Every announced nuclear-for-datacenter deal, converted into modeled pounds of uranium — the demand wave, quantified.

Download deal-book chartFree to share with attribution.

Cite this page

Using our data in an article or report? Please credit Yellowcake Analytics with a link.

Citation

Yellowcake Analytics. "Nuclear-for-AI Datacenter Deal Book." Yellowcake Analytics, 2026, https://www.yellowcakeanalytics.com/datacenter-deals.

HTML (with link)

<a href="https://www.yellowcakeanalytics.com/datacenter-deals">Nuclear-for-AI Datacenter Deal Book</a> — Yellowcake Analytics (www.yellowcakeanalytics.com)

The weekly uranium brief

Spot moves, SPUT flows, filings, and contract news, once a week. Plus a free daily CSV of our uranium equity screener snapshot.

Free forever. One email a week + a daily data CSV. By subscribing you agree to receive marketing email from Yellowcake Analytics (privacy policy). Unsubscribe anytime.